Walloon region halts Google data center construction over water permit

What happened
On November 26, 2026, the Walloon Region in Belgium ordered Google to stop construction at its data center in Aiseau-Presles after revoking an amended building permit. The permit was withdrawn due to concerns about water usage linked to a switch from air to water cooling during a period of drought. Greenpeace Belgium had requested an emergency halt after reporting that construction continued despite the permit's revocation. Legal proceedings are ongoing, with a public hearing scheduled for January 7, 2027.
Key details
- Google's original permit for three data centers was granted in 2024.
- The amended permit, approved in April 2026, merged two centers into one and changed the cooling system to water-based.
- The permit was revoked by Walloon minister François Desquesnes in August 2026 after resident appeals.
- Greenpeace reported that Google's existing Saint-Ghislain data center uses 1 billion liters of water per year for cooling.
- A Walloon government framework published on November 12, 2026, requires a partnership contract for data center projects over 25 megawatts.
Why it matters
Google must halt construction at the Aiseau-Presles site while the legal dispute over water usage and permitting continues, affecting its expansion plans in Belgium. Local residents, environmental groups, and regional authorities are directly involved in decisions about resource allocation and industrial development. Data center operators in Wallonia now face stricter requirements on water use and must secure regional partnership contracts for large projects, impacting future infrastructure planning.