IEA Scenario Links AI Growth to Doubling of Data Center Power Use

What happened
The International Energy Agency published its World Energy Outlook 2026 on November 19, 2026. In its Stated Policies Scenario, the agency projects that investments related to AI could double the global electricity consumption of data centers to 1,000 terawatt-hours by 2030. The scenario also anticipates that data-center capacity could reach nearly three times its current size by 2035. This expansion is expected to place significant demands on power grids, supply chains, and public acceptance, requiring large-scale upgrades and integration of renewable energy sources.
Key details
- About 16 million kilometers of existing power lines need replacement or refurbishment in the same period.
- Renewables are projected to supply half of global electricity generation by 2035 in this scenario.
- Grid spending is expected to rise by 75% over the next decade, even without new policy action.
- Peak electricity demand could grow by 40% to 50% by 2035 across scenarios.
Why it matters
Electric utilities, data-center operators, technology companies, and equipment suppliers face higher costs and logistical challenges to expand grid infrastructure and secure enough renewable energy. The need for more power lines, transformers, and other equipment could strain supply chains and require faster regulatory approvals. Communities near new or expanded data centers may encounter changes in local infrastructure and energy use, while investors and developers must prioritize power-system delivery as a central factor in AI infrastructure planning.