Mexico struggles to attract AI data centers due to power and permit issues

Covered by 2 sources
Read onThe Next Web· 2 min
Mexico is facing difficulties in expanding its AI data center industry because of an outdated electricity grid and slow permitting processes. Although its location near the US market is advantageous, power shortages and regulatory hurdles are limiting investment and development.

What happened

Mexico is having difficulty attracting new AI data center projects because its electricity grid is outdated and the process to get permits is slow. Although the country is close to the US and has favorable conditions for data transfer, it lags behind regional peers in the number of data centers. Private companies are investing in new power plants and infrastructure, but regulatory and capacity issues are causing delays. The government has plans to increase power generation capacity by 2030, but current rules require most of this to come from the state utility, limiting private sector involvement.

Key details

  • Mexico has 71 data centers, compared to 225 in Brazil and 66 in Chile.
  • CloudHQ has applied for around 111 permits for a $4.8 billion data center project in Querétaro.
  • It can take up to three years to secure an electricity connection contract for a data center.
  • President Claudia Sheinbaum aims to add about 32 gigawatts of new power capacity by 2030.

Why it matters

Companies planning to build or expand data centers in Mexico face higher costs and longer timelines due to power and permitting obstacles. Technology firms with climate targets may hesitate to invest without more renewable energy options. The slow pace of infrastructure development could limit Mexico’s share of the growing data center market, affecting potential economic gains and job creation.

Also covered by 1 source