Natural England objected to a datacentre. Weeks later ministers threatened to abolish the agency

What happened
Natural England formally objected to the construction of a 40MW AI datacentre at Avonmouth near Bristol, citing risks to protected wildlife and flood safety. The objection was made to Bristol city council, which was considering the planning application. Weeks later, UK ministers, including the de facto deputy prime minister, threatened to abolish Natural England and the Environment Agency, suggesting their responsibilities could be transferred to ministers or devolved authorities. This occurred as the government continued to promote the rapid expansion of AI datacentres across the country.
Key details
- The proposed datacentre is 600 metres from the Severn estuary special protection area and 270 metres from Hallen Marsh, both sites for protected wildlife.
- The Environment Agency also objected, citing flood risk and lack of information on water use and pollution.
- More than 4,000 people have lodged objections to the datacentre plan.
- There are over 300 AI datacentres awaiting grid connection in the UK, representing 73GW of demand.
- The government is allowing datacentre projects to use the nationally significant infrastructure projects regime, bypassing some local decision-making.
Why it matters
Developers of AI datacentres and local communities face changes in how environmental concerns are handled during planning, as the possible abolition of Natural England and the Environment Agency would shift oversight to ministers or devolved authorities. This could affect the level of independent scrutiny applied to projects that may impact protected habitats and flood safety. The decision also affects the pace and conditions under which hundreds of planned AI datacentres may proceed across the UK.