Statnett Pauses Data Center Grid Reservations Pending New Technical Rules

What happened
On November 9, 2026, Norway’s grid operator Statnett temporarily halted new grid-capacity reservations and paused parts of its facility-approval process for data centers. This action was taken due to a sharp increase in connection requests, with the pause expected to last until new technical rules for safe operation are established by August 1, 2027. The Norwegian government also announced a new licensing scheme for data centers, which will apply to both existing and future facilities. The measures are intended to manage the impact of large-scale data center demand on the national electricity grid.
Key details
- Statnett received requests for an additional 18,000 MW of data center connections.
- Norway’s current maximum power consumption is just over 25,000 MW.
- The pause does not affect existing connections or facilities with already approved requirements.
- Statnett currently has 800 MW of data center demand connected, 4,200 MW reserved, and 9,100 MW in the queue.
- The government’s licensing scheme will prioritize data centers that support AI computing and digital security.
Why it matters
Data center operators seeking to establish or expand in Norway now face a waiting period for new grid connections, which could delay projects until at least August 2027. Companies with existing approvals or smaller facilities may proceed, but new large-scale projects are on hold. The new licensing scheme and technical requirements mean that only data centers meeting specific criteria, such as supporting AI and digital security, will be prioritized, and large consumers may have to cover more of the infrastructure costs they generate.